Completion of a 125,000SF ultimate greenfield facility design in San Antonio, TX. The facility is planned for three phases with phase I comprising of 47,250SF of whitespace with the ability to add an additional 30,000SF. The facility was designed and constucted to Tier III standards with 5MW of generator capacity and 4kW of A/B (2+2) UPS capacity. The facility is managed from a 1,000SF NOC and 3,100SF Service Desk.

Services Provided during this engagement:

  • Site Selection
  • Engineering Design
  • Project Management
  • ¬†System Testing & Commissioning